Navigate to Network⇒Production⇒Split Job
This shows the Split Job List of all jobs available to be split – Double click on the Job number to be split
This opens the Split Quantity page
In Child Job 1, enter the quantity of the split job, select a reason for the split and split the serial numbers
Note – If the original quantity was entered with only one serial number, then this serial number can only be allocated to one of the newly split batches – the other split batch will have to be manually amended to put the serial number back on it
Then press Save
Child Job 2 will then be created with the remainder of the Quanity
Both jobs will now appear in the job list and the job card(s) can be printed (usually only the remainder – Child Job 2 – would be printed as the first split batch – Child Job 1 – would be on the original job card)